Power Grid diluting stake to raise funds for expansion
► Move surprises analysts as
the company has enough cash already
► Fears of a July 2012-like
grid failure prompt the PSU to plan strengthening measures
The government-owned power transmission utility Power Grid
Corporation of India (PGCIL) is planning to sell 694 million new shares, or 15
per cent of the existing stock, to fund the strengthening of the transmission
system and pre-empting blackouts in the country. Though the public sector unit
is not facing any issues on cash front, it wants to trim its equity to generate
the required cash for building a robust transmission system.
The Gurgaon-based company last month sold `3,970 crore of
bonds and now it plans to offer new shares to finance the additional
investment. The company had suffered lot of bad press last year after the
network collapse that had left more than half the nation’s population without
electricity. Power Grid will inject additional 10 per cent over and above the
already earmarked $16.5 billion investment to set up a system which is
fool-proof. About `10,000 crore will be spent in the five years till March 2017
to complete the projects, Chairman, PGCIL, R.N. Nayak told mediapersons
recently.
The company’s move to reduce equity has surprised industry
experts and analysts. It had earlier said that it was ready to change its 70:30
debt-equity mix to 75:25 and a share sale was not on cards in the year ending
March 31. The company is sitting on cash and equivalents of about `2,870 crore
and industry experts had expected it to use this cash to meet its funding
requirement.
“Although there had always been an overhang of a possible
equity dilution, we didn’t expect it to happen this year. They don’t have a
cash crunch,” says Anubhav Gupta, an analyst at Kim Eng Securities Pvt. in
Mumbai. The announcement of share sale has also surprised analysts as concerns
to avoid a large-scale grid failure had to an extent been addressed by putting
in place stringent restrictions. The public sector company has already prepared
a roadmap to double its transmission capacity and invest in systems to avoid a
similar blackout which had forced factories to shut, chocked transport and
created havoc in the investor community both within and outside India.
Penalties haven increased to discourage states from drawing power in excess of
their allocations, a breach which was probably the reason behind the northern
grid collapse last year.
However, outages continue to plague large swathes of the
country. “That’s not going to change in a hurry. States that now risk heavier
penalties for overdrawing power, are simply not buying enough,” says Debasish
Mishra, partner and head of energy practice at Deloitte Touche Tohmatsu India
Pvt. “At the same time, we have come a long way since last year’s blackouts…
grid discipline has increased significantly and chances of a second such
blackout are really thin,” adds Mishra.
Planned investment
The transmission behemoth would pump in `2,220 crore in the
current financial year ending March 31. The company had earlier planned to
invest `2,000 crore in the current financial year. It has so far raised `8,000
crore of debt in the year started April 1, Nayak said. The proceeds of the
share sale, which is estimated at `6,340 crore based on the current share
price, would be used to fund the equity portion of its investment plan for the
next three years, he said.
Power Grid plans to expand the network to 140,000 circuit-
kilometers by March 2017, he said. The company is developing 11 high capacity
transmission corridors to haul electricity from generation projects spread
across more than eight states, as per official statement. The company is also
building a transmission system for Tata Power, which has set up a 4,000
megawatt project at Mundra in Gujarat, and Reliance Power, which is building a
similar sized plant at Sasan in Madhya Pradesh.
“Power Grid’s project executions are timely and growth is
stable. A change in the negative sentiments about the power sector can trigger
an upgrade for the stock,” Gupta of Kim Eng Securities said.
Transmission loss
More than a quarter of the electricity generated in the
country is lost in transmission because of theft and dissipation through wires.
Distribution utilities, unable to retrieve their costs from
government-regulated tariffs, accumulate debt and cut purchases.
The country plans to spend 13.73 trillion rupees to expand
and upgrade its power systems by March 2017, with much of the investment coming
from generators including state-owned NTPC Ltd, Tata Power Ltd. and Reliance
Power Ltd. India currently has a capacity to generate almost 226 gigawatts,
plans to add 118 gigawatts of capacity during the period, including 30
gigawatts of renewable energy, according to the Planning Commission.
InfralinePlus Magazine (Editorial Team)

No comments:
Post a Comment