Friday, March 7, 2014

Roads Construction Data of NHAI : Far From Reality

The Indian road sector continued to face multiple challenges in this financial year in the form of high interest rates, sluggishness in award of road contracts, reduced availability of funds, execution slowdown, and increased competitive intensity. However, execution on many of the projects awarded over the last one year remained slow primarily because of delays in land acquisition, clearances, and financial closure. Projects that had the requisite approvals and funding reported healthy execution.

While both developers and contractors are going through a rough phase over the last one and a half years, the challenges were higher in the case of companies that had recently entered the project development space. While developers with a portfolio of operational toll road projects were partly hedged from high interest rates due to inflation-linked toll rates, those with projects in the developmental phase faced challenges in achieving financial closure due to weakened project viability owing to high interest rates besides delays in land acquisition and approvals. 

With NHAI increasingly awarding projects under the public-private partnership (PPP) model, engineering, procurement and construction (EPC) contractors have struggled to maintain their order-book growth. The equity requirement for BOT projects, along with the weak capital markets that have made raising capital difficult, has increased their dependence on external borrowings. Further, many of these companies have raised debt at the parent or holding company level to meet the equity requirement in BOT projects thus significantly increasing the indebtedness at the group level.

The details of allocation and expenditure for development / construction of NHs are as under:


Year
Allocation

Expenditure
2007-08
14,193.74
12,337.06
2008-09
17,522.26
14,670.86
2009-10
19,080.92
14,660.20
2010-11
25,526.80
19,617.34
2011-12
31,862.19
29,605.00
2012-13
29,438.05
19,499.76
2013-14#
34989.49
2864.48
# Expenditure up to June, 2013

NHAI awarded only 3,857 km during 2012-13 period. The comparatively lower quantum of award in previous years affected the completion rate. The targeted and completed length under various schemes including Special Accelerated Road Development Programme in North East (SARDP-NE) and Left Wing Extremism (LWE) during the last three years and the current year are as under:


Year
Target
(Length in km)
Achievement (Length in km)
Length Constructed per day
2009-10
5830
5164
14.15
2010-11
5534
4334
11.87
2011-12
5824
5013
13.73
2012-13*
6092
3857
12.60

The progress of construction of National Highways has been slow due to several problems such as land acquisition, shifting of utilities, environmental and forest clearance, approval for rail over bridges as well as shortage of skilled/semi-skilled manpower and economic slowdown. In order to expedite implementation of the Projects, Regional Offices have been set up by National Highways Authority of India (NHAI) headed by Chief General Manager. Powers have been delegated to the Chief General Manager who is involved in expediting forest / environmental clearances and monitor land acquisition matters as well as implementation of Projects. Special land acquisition units are also set up to expedite land acquisition. Chief Secretaries of State Government have also been nominated as Nodal officers to expedite Highway Projects. Projects are also closely and periodically reviewed at Headquarter as well as field units.


Recently, the issues of de-linking environmental clearance from forest clearance and exempting linear stretches from the requirement of NOC from Gram Sabha have been resolved. Reserve Bank of India has given dispensation to treat the debt due to lenders, to the extent assured by Project Authorities in terms of concession agreement, as secured loan. Disinvestment of 100% equity to other willing buyers has been allowed after completion of the construction and also substitution of concessionaire allowed after achievement of financial closure to salvage the languishing projects. The NHAI has also constituted Negotiation / Reconciliation Settlement Committees and also High Level Expert Settlement Advisory Committee to settle the claims / disputes. Further, Government has decided to award contracts on Engineering Procurement and Contract (EPC) basis also.

                                                  
                    Infraline Energy Roads Knowledgebase Team 
                  

No comments:

Post a Comment