To fast track the slow-moving sector and in order to provide
major relief to the companies the Finance Ministry approved the policy of
premium rescheduling as proposed by Rangarajan Committee report. The policy
proposal of MoRTH was based on the recommendations of NHAI Board, which in turn
had considered various representations made by concessionaires before
MoRTH/NHAI for some of the already awarded national highway projects through
PPP mode.
The aim of this proposed policy initiative is to increase
the pace of development of building highways infrastructure and facilitate
expeditious completion of awarded highway projects facing financial stress in
the current economic situation. Legal opinion in this regard from the Ministry
of Law & Justice (MoU) was also obtained before the final provisions were
submitted for consideration by CCEA.
The Highways sector in India is going through a difficult
phase. A host of factors, a few of which are sector specific and others which
are external and beyond the control of MoRTH/NHAI and Contractors / Developers,
have adversely affected the sector. For instance, in 2012-13, out of total
targeted award of around 8000 Km, the MoRTH/NHAI could award only 1322 Km of
highways on BOT (Toll) and the trend continues this year, as well. The ministry
has been able to award only 3,169 km of road projects in 2013-14 against a
target of 7,500 km.
To summarize, the main reasons leading to this dismal
situation for projects are:
- Overall economic downturn
- Lack of equity in the market
- Difficulty in arranging debt
- Highly leveraged balance sheets for highway developers
- Land acquisition & approval and clearance related issues
To address the above, MoRTH is taking conscious steps like
shifting focus from PPP projects to public funded EPC contracts as mode of
delivery, emphasis on land acquisition and qu ality of project preparatory
activities and facilitating policy level changes to make the environment more
conducive for developers/contractors.
One of such enabling initiatives is to consider
restructuring of premium payable by concessionaires of the projects awarded on
premium, to the Authority i.e. NHAI. Premium is an amount paid by the roads developing
developer to the National Highway Authority of India in PPP (BOT-Build, Operate
and Transfer) projects. It is based out of the estimated Toll revenue of
developers.
Rationalization of Premium
NHAI specify that there are 53 Highway Projects (4 laning as well
as 6 laning ones) which were awarded on a premium basis in recent past when
prevailing economic scenario was buoyant. Most of the concessionaires for such
projects have recently communicated to MoRTH/NHAI - their inability to honour
premium commitments upfront in the current economic environment in spite of
their earlier commitments in this regard as per the executed project concession
agreements. Because of this, many projects are delayed and it is feared that
the implementation for such projects could get postponed for an indefinite
period.
NHAI, for such projects, have two distinct options:
- Option 1 -To adopt the legally appropriate and technically straightforward choice of terminating such projects where the concessionaires are unable to fulfill their commitment of premium payments as stated at the time of bidding as per the terms of the contract.
- Option 2- To allow rationalization of project premium for all such premium bearing projects, wherein, the proposed premium offered to be paid by the concessionaire to the Authority during the bid stage may be allowed to be deferred towards the later part of the concession period. However, NPV of the total premium payable would remain the same.
Case Example: In case, the premium (P) quoted by the bidder is
greater or equal to the Toll (T) collected minus Debt (D) payment &
0&M(0) expenditure, the project is stressed one at that point of time. This
would imply that the concessionaire is required to borrow money from the lender
in order to pay premium to NHAI. The project will only be in a comfortable
position if premium quoted is less than the revenue earned minus debt payment
& O&M expenditure. Consistent negative cash flows based on the revenue
projected as per the traffic survey and the total project cost provided in
Financing document may also lead to a project to be the stressed one, as long
as estimated TPC by concessionaire is in the reasonable proximity of the TPC
approved by PPPAC/CCEA. Than the project would be considered for the
rescheduling of premium payment made to NHAI.
National Highways Authority of India or NHAI has approved
nine projects so far for deferment of premium repayment worth around INR 6,000
crore. Deferment would be available from 2014-15 till 2026-27. During 2014-15,
deferment amounting to INR 651 crore has been granted. There are two aspects
that NHAI looks into before deciding which projects can get deferment:
a) There has to be a clear and visible case of revenue
shortfall and
b) These companies should be able to repay the rescheduled
amount along with interest at least one year before the concession period ends
This decision of deferring premium payment could provide a
major boost up to infrastructure companies like GMR, GVK, Ashoka Buildcon,
IVRCL, Sadbhav Engineering and Gammon Infrastructure.
By
InfralineEnergy Roads Research Team
The
views expressed here are solely those of the author in his private capacity and
do not in any way represent the views of the Infraline Technologies (India)
Pvt. Ltd. (organization). The organization is not liable for any use that may
be made of the information contained therein and any direct/indirect
consequences resulting therefrom.
No comments:
Post a Comment